Concrete Slab Cost Calculator

Work out the cubic yards of concrete a slab needs from its area and thickness, then add your price per cubic yard and labor rate for a planning-estimate total.

Planning estimate: this is a planning estimate from the numbers you enter and standard reference quantities — not a bid or a contract. Get itemized written quotes from licensed contractors and confirm measurements before you commit.
Engineer & permits: Foundation movement, cracks, bowing walls and drainage problems should be assessed by a licensed structural or geotechnical engineer before repair. Structural, excavation and electrical work must be done by licensed professionals and usually needs a permit and inspection. Confirm scope, permits and code with your local building department before you start.

Calculator

sq ft
Length × width of the slab in feet
Typical planning thickness — 4 in is common for light-duty slabs
$
Your delivered ready-mix price per cubic yard
$/sq ft
Your rate to form, place and finish; leave 0 for concrete only
Estimated total$2,390.12
Concrete volume4.94 cu yd (400 sq ft × 4 in ÷ 12 ÷ 27)
Concrete$790.12 (× $160.00/cu yd)
Labor$1,600.00 (400 × $4.00/sq ft)

A 400 sq ft, 4-inch slab is 4.94 cubic yards of concrete ≈ $790.12 plus labor, about $2,390.12 total. Structural slabs need licensed pros and a permit.

A concrete slab is priced in two parts: the concrete itself, sold by the cubic yard, and the labor to form, pour and finish it, usually figured by the square foot. The trick that trips people up is the volume — ready-mix comes in cubic yards, but a slab is measured in square feet and inches of thickness. This calculator does that conversion for you, then multiplies by the delivered price and labor rate you enter. Nothing about local material prices is baked in; you supply those from your own quote.

It suits any flat pour where you know the footprint and thickness: a shed or garage floor, a basement slab, a patio, an equipment pad. Enter the area, pick a thickness, and the tool returns the cubic yards to order plus a total. Because the geometry never changes and every dollar is yours, the answer stays correct year after year with no maintenance.

Formula

Turn area and thickness into cubic yards, then price the concrete and add labor:

volume_cu_yd = area × (thickness_in ÷ 12) ÷ 27\ncost = volume_cu_yd × price_per_cuyd + area × labor_per_sqft

The thickness is converted from inches to feet (÷ 12), multiplied by the area to get cubic feet, then divided by 27 because there are 27 cubic feet in a cubic yard. That is the standard planning volume — order a little extra for spillage, uneven subgrade and over-dig. The labor term is a straight area × your $/sq ft; set it to 0 if you only want the material volume and cost.

Worked example

A 400 sq ft slab, 4 inches thick, with ready-mix quoted at $160 per cubic yard and finishing labor at $4 per square foot:

  • Volume = 400 × (4 ÷ 12) ÷ 27 = 4.94 cu yd
  • Concrete = 4.94 × $160 = $790.12
  • Labor = 400 × $4 = $1,600
  • Total = 790.12 + 1,600 = $2,390.12

Bump the thickness to 6 inches and the volume rises to 7.41 cu yd (concrete about $1,185), because you are pouring half again as much material. Thickness drives the concrete cost directly, which is why the reference table below is worth a look before you order.

Ordering concrete, thickness and the structural line

Always order a little extra. The 4.94 cubic yards in the example is the exact geometric volume; real subgrade is never perfectly flat, forms bulge slightly, and a bit is lost to the chute and cleanup. A common planning move is to round up and add roughly 5–10% so you are not stopping a pour a quarter-yard short — there is no good way to add fresh concrete to a slab that has started to set. Enter your own rounded volume if your supplier sells in half-yard increments.

Thickness is the big lever. Four inches is a typical planning thickness for light-duty flatwork like a patio or shed floor; heavier loads — a driveway that takes trucks, a garage, an equipment pad — often call for 5 or 6 inches, and the concrete cost rises in step because volume is linear in thickness. The right thickness, along with any reinforcing steel, control joints, vapor barrier and base preparation, depends on what the slab carries and your local code, none of which this calculator decides for you.

That is why a slab that does real structural work — a footing-supported floor, a slab tied into a foundation, anything bearing a building load — needs a licensed professional and usually a permit and inspection. Confirm the required thickness, reinforcement and base with your engineer or building department before you pour. Treat the figure here as a planning estimate for budgeting and for ordering material, not as an engineering specification or a contractor's bid.

Frequently asked questions

How many cubic yards of concrete do I need for a slab?
Multiply the area in square feet by the thickness in feet (inches ÷ 12), then divide by 27. A 400 sq ft slab at 4 inches is 400 × 0.333 ÷ 27 = about 4.94 cubic yards. Order a little more than the exact figure — roughly 5 to 10 percent — to cover spillage and an uneven base, because you cannot top up a slab that has started to cure.
What thickness should my slab be?
Four inches is a common planning thickness for light-duty flatwork like patios and shed floors; driveways, garages and pads that carry vehicles or heavy loads are often 5 to 6 inches. The correct thickness, plus any rebar or mesh and the base prep, depends on the load and your local code — confirm it with a pro rather than guessing from the calculator.
Does the price per cubic yard include delivery?
It depends on your supplier. Some quote a delivered price per cubic yard; others add a delivery or short-load fee, especially for pours under a full truck. Ask what the per-yard figure covers and, if delivery or a small-load charge is separate, fold it into the labor line so your total is complete.
Why is labor figured per square foot, not per cubic yard?
Forming, placing and finishing a slab is surface work — screeding, floating, edging and jointing all scale with the area, not the volume. So crews commonly quote finishing by the square foot. Enter your finishing rate there, or set it to 0 if you only want the concrete material volume and cost.
Is this the same as the cost to pour a foundation slab?
The volume math is identical, but a structural slab — one bearing a building load or tied into a foundation — needs engineered thickness, reinforcement and base preparation, plus a permit and inspection. Use the volume here for budgeting and ordering, but have a licensed professional specify a structural pour.